A 50 ft × 6 ft area covered 12 inches thick needs about 11.1 cubic yards of riprap. At 1.5 tons per cubic yard, that's roughly 16.7 tons. The layer is usually 1.5–2 times the stone's D50 size. Enter your measurements and stone class below.

Area & layer
ft
ft
in

Density & waste
t/yd³
%
$/ton
Riprap needed
18.3tons
12.2 cu yd (incl. 10% waste).
Cubic yards
12.2 cu yd
Base (no waste)
11.1 cu yd
Show the math
area = 300 sq ft
cubic yards = area × (12 ÷ 12) ÷ 27 = 11.1
+ 10% waste = 12.2 cu yd
tons = 12.2 × 1.5 = 18.3

How to use this calculator

  1. Enter the length and width (or slope length) of the area.
  2. Set the layer thickness in inches.
  3. Pick a stone size class, or enter a custom density.
  4. Add a waste allowance for voids and uneven placement.
  5. Read cubic yards and tons.

Formula

cubic yards = length × width × (thickness ÷ 12) ÷ 27
tons = cubic yards × density (≈ 1.5 tons per cu yd)
layer thickness ≈ 1.5–2 × stone D50

Worked example

A 50 ft × 6 ft area, 12 inches thick:
volume = 300 × 1 = 300 cu ft
cubic yards = 300 ÷ 27 = 11.1
tons = 11.1 × 1.5 = 16.7 tons

Second example

A 30 ft × 8 ft slope, 18 inches thick:
area = 30 × 8 = 240 sq ft
volume = 240 × (18 ÷ 12) = 360 cu ft
cubic yards = 360 ÷ 27 = 13.33 ≈ 20 tons
Rip rap calculator diagram of a stone layer on a slope with thickness labelledLengthWidthDepth
Rip rap calculator diagram of a stone layer on a slope with thickness labelled

What this calculator doesn't cover

This is a quantity estimate, not a hydraulic design. Stone size and thickness for streams, channels and shorelines should come from an engineer or your state DOT specification.

Reference tables

Typical riprap stone classes
ClassD50 sizeLayer thickness
Light / Class I4–6 in12"
Medium / Class II9–12 in18"
Heavy / Class III15–18 in27"

Classes and gradations vary by state DOT. Confirm against your local specification.

Riprap tons by area and thickness (1.5 t/yd³)
Area12"18"24"
100 sq ft5.68.311.1
200 sq ft11.116.722.2
300 sq ft16.725.033.3
500 sq ft27.841.755.6

At about 1.5 tons per cubic yard; one ton covers roughly 18 sq ft at 12 inches thick.

Tips & buying advice

  • Lay riprap over filter fabric or a gravel filter layer. Without it, the soil underneath washes out through the gaps.
  • Make the layer at least 1.5 times as thick as the largest stone so the stones lock together.
  • On a slope, dig the bottom edge (the toe) in below grade so the whole layer doesn't slide.
  • Order about 10% extra. Angular stone leaves gaps, and no one places it perfectly even.

For shoreline or channel work, follow your engineer or local permit requirements.

Frequently asked questions

How much area does a ton of riprap cover?
At 12 inches thick and about 1.5 tons per cubic yard, one ton covers roughly 18 square feet. A thinner layer covers more. At 6 inches, it's about 36 square feet per ton.
What size riprap do I need?
It depends on how fast the water moves and how steep the slope is. Light classes (4–6 inch stone) work for gentle ditches and low banks, and heavier classes hold up against faster water. For streams, channels or shorelines, follow an engineer's or your state DOT's specification.
How thick should riprap be?
At least 1.5 to 2 times the D50 stone size, and never thinner than your biggest stone. A typical light riprap layer is about 12 inches. Heavier classes run 18 inches or more.
Do I need filter fabric under riprap?
Almost always. Filter fabric or a gravel filter layer keeps the soil underneath from washing out through the gaps between the stones. If that soil goes, the riprap sinks. Overlap the seams generously.
How much does riprap cost per ton?
In 2026, riprap usually runs about $45–$100 per ton delivered. Where you land depends on the stone class, how far the quarry is and how much you buy. Get a local quote, since the trucking distance drives a lot of the price.
How many tons of riprap do I need per square foot?
At 12 inches thick and about 1.5 tons per cubic yard, you need roughly 0.056 tons, or about 110 lb, per square foot. So 100 square feet at 12 inches comes to about 5.6 tons. Thicker layers need proportionally more.
How much riprap do I need for a 100-foot shoreline?
For a 100-foot shoreline 6 feet wide (600 sq ft) at 18 inches thick, you need about 33 cubic yards, or 50 tons, at 1.5 tons per cubic yard. Check the thickness and stone class with your engineer or permit office before you order.
Landscaping Material
Crushed Stone Calculator

How much crushed stone by size (#57, #411, crusher run): tons, cubic yards, truckloads and cost.

Open calculator →
Landscaping Material
Gravel Calculator

How much gravel for a driveway, path or patio: cubic yards, tons, bags and cost.

Open calculator →
Landscaping Material
Cubic Yard Calculator

Area and depth to cubic yards, tons and bags for any loose material.

Open calculator →
Landscaping Material
Pea Gravel Calculator

Pea gravel cubic yards, tons and bags by area and depth.

Open calculator →
Landscaping Material
Landscape Material Calculator

Yards, tons and bags for mulch, rock, soil, sand and more.

Open calculator →

Sources

Built and maintained by Sikander Mushtaq. Formulas checked against state DOT riprap gradation tables, USACE/FHWA riprap design guidance. See our methodology and sources, or learn about YardageMath. See our editorial policy.

Last updated:

Estimates only. Confirm quantities with your supplier or contractor. Read the full disclaimer.

← Back to Landscaping Material Calculators